The contractor finished up the upper cabinet mouldings and started to fit the underside of the wall cabinets with finished panels for the recessed puck light fixtures. The panels are being put up temporarily so that holes can be cut for the light fixture spacing. On Monday, the remaining panels will be fitted and the electricians are scheduled to complete their electrical fixture wiring and hookup to the kitchen appliances.

Floor refinishers setting up their equipment

Heavy sander with little dust created

Vacuuming a must while sanding.

Orbital sanders are used in removing the old floor finish

Hand sanding also is done

First coat of polyurethane is applied to dry. Tomorrow
the second coat will be applied

Panel being cut after measurements were made


Underside panel being fitted and scribed to the wall

Finished underside panel temporarily in place for
light puck fixture installation